Malcolm X Sprinkler And Fire Alarm Installation:
This work will involve the installation of a new water main that will cross Washington Terrace.
|
5/26 - 8/8/03
|
200 High St Sprinkler And Fire Alarm Installation:
This work will involve the installation of a new water main that will cross High Street.
|
5/26 - 8/8/03
|
151 Church St Sprinkler And Fire Alarm Installation:
This work will involve the installation of a new water main that will cross Church Street.
|
5/26 - 8/8/03
|
Foss 7 New Hot Water Heaters In Mechanical Room:
|
5/27 - 6/20/03
|
Foss 4 Sanitary Line Installation:
|
5/26 - 6/20/03
|
CFA Zilkha Gallery HVAC Upgrade, New Finish Installation And Elevator Cylinder Replacement And Elevator Pump Changeout: Impacts Use Of Zilkha 106 And Zilkha 202.
|
5/26 - 10/15/03
|
CFA Art Workshops Fire Alarm Installation:
|
5/26 - 6/20/03
|
CFA Crowell Concert Hall Fire Alarm Installation:
|
5/26-5/28; 5/30-6/2, 6/3 (11:00 am)-6/20 & 8/4-8/22/03
|
CFA Music Studios Roof Hatch Access (Platform And Ladder Installation):
|
5/26 - 6/20/03
|
CFA World Music Roof Repairs:
|
10/20 - 10/22/03
|
CFA Theater Stairwell Doors Replacement:
|
8/4 - 8/22/03
|
William Street Highrise Apartments New Elevator Controller Installation:
|
6/2 - 7/18/03
|
Park Washington Apartments Elevator Cylinder Replacement:
|
7/15 - 8/15/03
|
SLF Woodframe Houses On MM Priority List:
|
6/2 - 8/8/03
|
William Street Lowrise Unit E Shower Enclosure Repair:
|
6/2 - 6/20/03
|