Current Scheduled Dates Of Buildings That Will Be Offline For Some Period Of Time During The Annual Major Maintenance May 2003 - May 2004

Dates are Subject to Change

Additional locations and dates will be added as contractors are awarded and dates are negotiated with the respective building occupants.

 

 

Building Identification

Dates Offline

Malcolm X Sprinkler And Fire Alarm Installation:

This work will involve the installation of a new water main that will cross Washington Terrace. 

5/26 - 8/8/03

200 High St Sprinkler And Fire Alarm Installation:

This work will involve the installation of a new water main that will cross High Street.

5/26 - 8/8/03

151 Church St Sprinkler And Fire Alarm Installation:

This work will involve the installation of a new water main that will cross Church Street.

5/26 - 8/8/03

Foss 7 New Hot Water Heaters In Mechanical Room:  

5/27 - 6/20/03

Foss 4 Sanitary Line Installation:  

5/26 - 6/20/03

CFA Zilkha Gallery HVAC Upgrade, New Finish Installation And Elevator Cylinder Replacement And Elevator Pump Changeout: Impacts Use Of Zilkha 106 And Zilkha 202.

5/26 - 10/15/03

CFA Art Workshops Fire Alarm Installation:  

5/26 - 6/20/03

CFA Crowell Concert Hall Fire Alarm Installation:

5/26-5/28; 5/30-6/2, 6/3 (11:00 am)-6/20 & 8/4-8/22/03

CFA Music Studios Roof Hatch Access (Platform And Ladder Installation):  

5/26 - 6/20/03

CFA World Music Roof Repairs:  

10/20 - 10/22/03

CFA Theater Stairwell Doors Replacement:  

8/4 - 8/22/03

William Street Highrise Apartments New Elevator Controller Installation:

6/2 - 7/18/03

Park Washington Apartments Elevator Cylinder Replacement:

7/15 - 8/15/03

SLF Woodframe Houses On MM Priority List:

6/2 - 8/8/03

William Street Lowrise Unit E Shower Enclosure Repair:

6/2 - 6/20/03

Hit Counter

Check page often for updates.

Return to MM FY03/04 project list